Some CW Heintz Construction Services and CW Heintz Past Projects & Experience

Universal Studios Florida

Scope

100-acre site. Infrastructure, including roads, utilities, parking lots, walk area, and lagoons. 60+ buildings and rides, including Jaws, King Kong, Back to the Future, ET, Hanna Barbera, restaurants, and gift shops. Provided construction inspections.

Timeline:30 months
Value:$900 million
POC:Mike Miller
 

Theme Park Fireworks Compound

Scope

Construct thirteen (13) pre-engineered metal storage buildings, along with associated roadways and utilities. The project included the installation of approximately 10,000 LF of fire and water pipeline.

Timeline:6 months
Value:$3 million
POC:Ray Bagshaw
 

Walgreens Drug Store

Scope

Construct a 15,000 SF concrete block building along with associated roadways and utilities. This project included the improvements to off-site roadways.

Timeline:5 months
Value:$1.2 million
 

Sunland Hospital

Scope

Demolition of 1940s era facilities. Project included a five-story and seven-story structure. Land area covered 48,000 square feet. Hazardous materials remediation involving lead, asbestos, and DDT was performed prior to demolition of building. Park facility built subsequent to building demolition.

Timeline:210 days. Completed on time and within budget parameters
Value:$1.5 million
POC:Department of Juvenile Justice, State of Florida